CMNEX019 gives will be called before/after checkout and before/after checkout.

But when performin a "stage" of a non-SRC component the exit CMNEX019 is also called.

 

When a component is modified and saved, the exit is called and the checkin indicators are enabled.

This is indepedent for a like-SRC component or a non like-SRC component.

When a like-SRC component is "staged" (so no change took place) the exit is not called (obvious as no checkin took place)

However when a non like-SRC is "staged" (so no change took place) the exit is called and the checkin indicators are enabled.

To better differentiate CHECKOUT/CHECKIN/BUILD it would be nice to see an additional indicator in the exit

eg. x19$sbld and x19$ebld (before and after build - aka stage)

For a like-SRC this would be just before the kickoff of the file tailoring

For a non like-SRC as it is performing today. 

Status: Delivered

Delivered

CMNEX019 gives will be called before/after checkout and before/after checkout.

But when performin a "stage" of a non-SRC component the exit CMNEX019 is also called.

 

When a component is modified and saved, the exit is called and the checkin indicators are enabled.

This is indepedent for a like-SRC component or a non like-SRC component.

When a like-SRC component is "staged" (so no change took place) the exit is not called (obvious as no checkin took place)

However when a non like-SRC is "staged" (so no change took place) the exit is called and the checkin indicators are enabled.

To better differentiate CHECKOUT/CHECKIN/BUILD it would be nice to see an additional indicator in the exit

eg. x19$sbld and x19$ebld (before and after build - aka stage)

For a like-SRC this would be just before the kickoff of the file tailoring

For a non like-SRC as it is performing today. 

ENH316310 is open for this request.

Status: Delivered

Delivered

CMNEX019 gives will be called before/after checkout and before/after checkout.

But when performin a "stage" of a non-SRC component the exit CMNEX019 is also called.

 

When a component is modified and saved, the exit is called and the checkin indicators are enabled.

This is indepedent for a like-SRC component or a non like-SRC component.

When a like-SRC component is "staged" (so no change took place) the exit is not called (obvious as no checkin took place)

However when a non like-SRC is "staged" (so no change took place) the exit is called and the checkin indicators are enabled.

To better differentiate CHECKOUT/CHECKIN/BUILD it would be nice to see an additional indicator in the exit

eg. x19$sbld and x19$ebld (before and after build - aka stage)

For a like-SRC this would be just before the kickoff of the file tailoring

For a non like-SRC as it is performing today. 

This request has been delivered in ZMF 8.2 Patch 1.