Problem:
Wants the import date/time stamp that is shown in the project manager.
Resolution:
To get the time/date stamp:
Select a copybook
show selected:<hasa:>attr_reql_name
It comes back as a integer which is "unixtime"(the number of seconds from Jan 1 1970 I think).....from there it will be necessary to format it into a human readable string.
To convert it do the following:
>>show selected:<hasa
system_date-time : 944681089
>>show convertdate(atoi(selected:<hasa:>attr_reql_name))
Wednesday, December 08, 1999 , 02:24:49 PM
#SupportTip
#EnterpriseAnalyzer